New Detached ADU in Miami, FL: What It Costs and How Long It Takes
A new detached ADU in Miami is a fully separate, self-contained home built on your lot, and the realistic all-in number runs $53,100 – $153,400. That covers design coordination, permits, site work, foundation, structure, roof, and finishes for a structure in the 500 to 900 square foot range. From a signed contract to a move-in-ready unit, most Miami detached ADUs take 6 to 10 months, and storm season is the variable that pushes good timelines into the longer end. Call (833) 630-4214 and we’ll walk your lot and give you a real number.
How we build a new detached ADU in Miami, stage by stage
Every new detached ADU follows the same rough order. The durations are honest: they assume a normal lot, a set of plans that doesn’t get kicked back, and a summer that behaves.
- Stage 1 – Site walk and feasibility, week 0 to 1. We look at setbacks, where the sewer or septic connection will run, how a crew and a crane will access the back yard, and whether an oak’s root zone sits where the slab needs to go. You decide the footprint and the orientation. This is the stage where most budget surprises get caught before they cost anything.
- Stage 2 – Plans and permitting, weeks 1 to 8 (or longer). Drawings get stamped, then the package goes to Miami-Dade County for building, zoning, and the wind-load review that every structure here has to clear. You decide finish level and elevation style now, because changes after permit are expensive. Under the High Velocity Hurricane Zone rules, every window, door, and roof assembly needs a Miami-Dade product approval, and we confirm those NOA numbers before submittal, not after.
- Stage 3 – Site prep and foundation, weeks 8 to 12. Clearing, grading, utility trenching, and a monolithic slab or stem-wall foundation. Inspections happen before the pour. You need to have chosen floor elevations and door swings by now, because they get set in concrete.
- Stage 4 – Structure, roof, and rough-ins, weeks 12 to 24. CBS block or wood frame goes up, tie-downs and straps get installed and inspected, the roof gets dried in with its impact-rated covering, and electric, plumbing, and HVAC get roughed. You pick fixtures and finishes here so ordering lands ahead of the finish crew.
- Stage 5 – Finishes, punch list, and final inspection, weeks 24 to 40. Drywall, paint, cabinets, tile, trim, and hookups. Then the final walkthrough where you and a lead walk the unit with a list. Our 730-Day Done Right Promise starts at completion, not at handoff paperwork, so if something settles or fails, we make it right.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The options you’ll choose between on a new detached ADU
These are the decisions that actually change the number. We’ll lay each one out with the honest trade-off before you commit.
- Block and stucco (CBS) vs. wood frame. CBS runs roughly 10 to 20 percent more up front but handles salt air, humidity, and wind-borne debris better, and it matches most Miami masonry homes. Wood frame builds faster and costs less in materials; it needs excellent moisture detailing to survive our climate.
- Roof assembly. Standing-seam metal holds up to UV and salt and has the longest service life, at the top of the roof budget. Impact-rated shingle systems cost less and meet code; the honest question is longevity and how often you want to revisit it.
- Impact windows vs. shutters. Impact-rated glazing is a larger single line item but simplifies hurricane prep and insurance. Roll-down or accordion shutters cost less up front but need maintenance in salt air and get deployed every storm.
- Layout: one-bed vs. two-bed. Two bedrooms plus a bath and kitchenette lands in the middle of the range; a one-bed studio comes in lower but sits harder to rent if the plan ever changes.
- Kitchenette and bath finshes. Standard cabinet lines and mid-grade quartz keep you in budget. Premium stone and custom cabinetry move you toward the top of the range.
- Utilities. Shared meters are simpler and cheaper; a separate meter for the ADU adds cost and coordination with the utility but is often what a rental or family use actually wants.
What New Detached ADU costs in Miami, FL

Plan on $53,100 – $153,400 for a new detached ADU in Miami. That range covers a fully permitted, move-in-ready unit from site prep through final inspection. Where you land inside it depends on five things:
- Size and complexity. A compact one-bed studio sits at the low end; a two-bed with a full kitchen and laundry pushes toward the top.
- Site conditions. A flat lot with easy access is one number. A tight lot with a long utility run, mature trees to protect, or a lift/crane-only access point is another.
- Structural and utility tie-ins. A short run to the main house panel and sewer is simpler; extending a panel, adding a dedicated meter, or a long trench moves the price.
- Finish grade. Cabinet, counter, tile, and fixture selections swing the total by tens of thousands.
- Permit and engineering scope. Site surveys, wind-load engineering, elevation certificates, and any flood-zone documentation all factor in, and we list them in writing.
Every estimate we give is line-item, so you can see the line you’re paying for and the line you’re choosing. The number you see is the number you pay.
See the difference
Before
After
Before
After
Before
AfterWhat Miami homes specifically do to this job
Miami is the hardest place in the country to build a detached structure, and that’s a fact, not a sales line. Miami-Dade County sits inside the High Velocity Hurricane Zone, and the wind-borne debris and product-approval rules here are stricter than anywhere else in Florida. Every window, door, and roof covering on your new detached ADU needs a Miami-Dade Notice of Acceptance on file, and the plans get reviewed to a code that doesn’t exist in Orlando or Tampa. If the structure sits on an older Miami lot, we also look at the main house, because in older neighborhoods like Little Havana and Edgewater we routinely find original 1920s CBS block walls with no continuous reinforcement or tie-downs, and any re-permit on the main roof can trigger a wind-mitigation retrofit. Salt air and year-round humidity mean every fastener, hinge, and strap we spec is rust-resistant, and every wall assembly is detailed for moisture. Storm season runs June through November, and good schedules bend around it. We work throughout Miami, including the 33173, 33112, 33169, and 33163 areas, and you can see the wider scope on our Home Additions & ADU in Miami page.
Serving Miami, FL – Our Local Coverage Area
We serve Miami and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked – New Detached ADU in Miami

Plan on 6 to 10 months, with permitting and storm season as the two biggest variables. Miami-Dade’s wind review can add weeks if the drawings aren’t ready with product approvals in hand. We give you a written schedule with the contract and update it at each stage. Call (833) 630-4214 to talk through your timeline.
Yes. A new detached ADU is a new residential structure and requires full permitting through Miami-Dade County, including building, zoning, and wind-load review. We handle the permit package, the inspections, and the sign-off as part of the job, and we don’t start framing until the permit is in hand. Call (833) 630-4214 for a permit walkthrough.
Yes, and many Miami homeowners do exactly that by reading the ADU as a separate service run off a new meter. Connecting to the main house panel and sewer is usually cheaper up front but ties the two structures together. Both are options, and we’ll price both in writing. Call (833) 630-4214 to talk through which fits your lot.
A new detached ADU in Miami runs $53,100 – $153,400, and our line-item estimate holds. If a site condition shows up that couldn’t be seen before we opened the ground, we stop, show you, and get your approval before any change. No surprise numbers. Call (833) 630-4214 for a free on-site estimate.
Every new detached ADU we build is covered by our 730-Day Done Right Promise. If workmanship fails in that window, we make it right, and the promise attaches to the ADU itself so it protects the structure, not just the paper. Call (833) 630-4214 to hear the details in plain English.
Get a free estimate for your new detached ADU in Miami
Call (833) 630-4214 to schedule a free on-site estimate for a new detached ADU in Miami. A live person answers any hour, walks your lot with you, and follows up with a written line-item quote covering every stage from permit to final inspection. If you’re already planning wider work, you can see the full scope on our Home Additions & ADU service, our Miami coverage page, and homeowners often pair this with Concrete Driveways & Concrete Work in Miami or a fresh Paver Driveways in Miami to finish the yard.