Garage Conversion ADU in Miami, FL: What It Takes and What It Costs
A garage conversion ADU in Miami typically runs $53,100 to $153,400 and takes three to six months from first permit submittal to final inspection. The work turns an existing attached or detached garage into a legal, permitted living unit: new framing and insulation, a full bathroom, a kitchenette, electrical and plumbing upgrades, and a Miami-Dade NOA-approved door and window package. It’s rarely a quick flip. Call (833) 630-4214 and we’ll walk your garage and give you a written, line-item estimate before you commit to anything.
How a garage conversion actually moves, stage by stage

We run garage conversions in a fixed sequence. Each stage has a real duration, and each one asks you to make a decision you can’t put off. Here’s what your calendar looks like.
Stage 1: Feasibility and permit submittal (2 to 5 weeks). We measure the slab, check ceiling height against the Florida Building Code minimum for habitable space, and confirm whether the existing footing and wall ties will carry the conversion. On a Miami garage, this is where we find out if the slab needs a moisture barrier or a topping pour. You decide here whether the unit is a studio or a one-bedroom, because that changes everything downstream.
Stage 2: Demolition and shell prep (1 to 2 weeks). Out goes the overhead door, the old service door, and any termite-damaged framing. We sister or replace studs, install new sill plates, and seal the slab. If your garage shares a wall with the house, we open the connection for the unit’s access door and rough that in now. This is the stage where surprises live: rotted bottom plates behind stucco in a 1960s CBS garage are common.
Stage 3: Rough-in trades and inspection (3 to 5 weeks). Framing, electrical, plumbing, and mechanical rough-ins go in, then we schedule the county inspection before anything gets closed up. You pick the bathroom fixture layout and the location of the kitchenette here, because moving a drain after the slab is cut doubles the plumbing line. This is the single most expensive decision point on the job.
Stage 4: Insulation, drywall, and finishes (4 to 6 weeks). Spray foam or batt insulation, drywall, tape and texture, then tile, flooring, cabinets, and paint. We source finishes from our partner brands so the spec sheet matches what actually shows up. Your decisions cluster here: flooring material, cabinet grade, tile, paint color, and the door and window package.
Stage 5: Final inspection and punch list (1 to 2 weeks). The county signs off, we walk the unit with you, and we fix everything on the list before we call it done. Our 730-Day Done Right Promise covers workmanship from that walkthrough forward.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The choices you’ll actually make on a garage conversion
Most of the budget swings come down to five or six decisions. Here’s the honest trade-off on each.
- Overhead door opening: A walled-in, insulated 2×6 frame with impact-rated glazing over the old opening is the standard and the sturdiest. A roll-up impact door keeps a garage function on one side but limits furniture layout. A fixed impact window wall gives the best light at the highest cost.
- Impact-rated glazing: Miami-Dade NOA-approved windows and doors are required here, not optional. Expect that line to run higher than a standard Florida window package. It’s the biggest single line that separates Miami from anywhere north of the county line.
- Flooring: Luxury vinyl plank over a sealed slab is the most cost-effective and handles humidity well. Porcelain tile lasts longer and feels cooler underfoot. Polished concrete is the cheapest durable option and holds up in a utility or studio unit.
- Bathroom and kitchenette level: A compact shower, a vanity, and a two-burner cooktop with a bar sink keep the plumbing footprint tight. A full tub-shower and a real range push the line up but rent for more.
- HVAC: A ducted mini-split or a dedicated ductless system is typical for a garage unit because tying into the house system rarely works with the existing load. Ductless is simpler to permit and service.
- Entry configuration: Interior access through the house is convenient but adds a fire-rated door and a framed opening. A separate exterior entry door is a simpler permit and better for privacy.
Brands that come up naturally on this job include Tremron and Techo-Bloc for the exterior walkway and patio that usually gets built alongside the unit.
What Garage Conversion ADU costs in Miami, FL

Plan on $53,100 to $153,400 for a permitted garage conversion ADU in Miami. The low end covers a studio layout in a sound attached garage with the bathroom and kitchenette kept tight. The high end covers a one-bedroom in a detached garage with new impact glazing throughout, a full kitchenette, structural retrofit work, and premium finishes.
| Line item | Typical Miami range |
|---|---|
| Demolition, framing, shell prep | $6,500 – $16,000 |
| Electrical, plumbing, mechanical rough-in | $9,000 – $24,000 |
| Impact-rated doors and windows (NOA-approved) | $8,000 – $22,000 |
| Insulation, drywall, texture | $5,500 – $13,000 |
| Bathroom build-out | $8,000 – $20,000 |
| Kitchenette, cabinets, counter | $6,000 – $18,000 |
| Flooring and finishes | $4,500 – $12,000 |
| HVAC (ductless or mini-split) | $4,000 – $9,500 |
| Permits, plans, inspections | $2,500 – $7,000 |
Five variables push a job toward the high end: the size and structural condition of the garage, how far the plumbing has to run from the house, whether the slab needs a new moisture barrier, the grade of impact glazing and finishes, and how much of the original structure fails inspection. A 1920s CBS garage in Little Havana will land higher than a 2005 block garage in a newer subdivision.
Your written estimate itemizes every one of those lines. What typically isn’t included: upgrades you add after the permit is pulled, landscaping beyond the immediate work area, and any utility upgrade the county requires once the unit’s load is calculated. We give you the number upfront and we hold it. Call (833) 630-4214 for the estimate.
See the difference
Before
After
Before
After
Before
AfterWhat Miami homes specifically do to this job
Miami sits in the High Velocity Hurricane Zone, and Miami-Dade County enforces the strictest wind-borne debris and product-approval rules in the country. Every door, every window, and every glazed opening on your converted unit needs a Miami-Dade NOA approval, and the inspector will check the label. That’s a different code from the rest of Florida, and it’s why a garage conversion here costs more and takes longer than the same job in Orlando.
Then there’s the housing stock. In older neighborhoods like Little Havana and Edgewater, we routinely open up a garage and find original 1920s CBS block walls with no continuous reinforcement or tie-downs. That triggers a full wind-mitigation retrofit once the conversion is re-permitted, and it’s the single biggest cost surprise on the job. Out near Miami Springs and Coral Gables, the 1960s concrete-block garages are usually better tied but more likely to have rotting bottom plates and old cast-iron or gray plumbing that has to be re-run. Salt air eats fasteners and hardware, so we spec rust-resistant hardware throughout, and we schedule exterior work around the June-to-November storm window rather than fighting it. Our team working across Miami knows what the inspector is going to look for before the first nail goes in.
Some homeowners pair the conversion with a new Concrete Driveways & Concrete Work in Miami pour or a resurfaced Asphalt Driveways & Resurfacing in Miami to make the new entry read cleanly from the street. If your garage conversion is part of a larger scope, that work lives on our Home Additions & ADU in Miami page, and you can see the full breadth of our Home Additions & ADU service there.
Serving Miami, FL – Our Local Coverage Area
We serve Miami and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked about Garage Conversion ADU in Miami

Three to six months from permit submittal to final inspection is typical for a garage conversion ADU in Miami. The county review alone usually takes two to five weeks, and the real driver is how fast you make the finish decisions during rough-in. Call (833) 630-4214 and we’ll give you a schedule built around your garage, not a generic one.
Yes. Miami-Dade County requires a permit for any garage conversion, and the unit is inspected as a habitable space with its own electrical, plumbing, and life-safety requirements. Doing it without a permit risks a stop-work order and creates a real problem when you sell. We pull the permit and pass the inspections as part of the job.
Usually yes on the plumbing, if you stack the bathroom and kitchenette against the wall nearest the house. Structure is a different answer. Any new opening in a shared wall or any wall removal on a garage conversion needs an engineer’s sign-off, and in Miami’s HVHZ that also means wind-mitigation review. Call (833) 630-4214 for an on-site look before you assume the layout is free.
The full range for a permitted garage conversion ADU in Miami is $53,100 to $153,400, and the number moves most on glazing grade, plumbing distance, slab condition, and finishes. Call (833) 630-4214 for an exact quote. Estimates are free and itemized.
Every garage conversion we build is covered by our 730-Day Done Right Promise: if it isn’t done right, we make it right, for two full years after the final walkthrough. That’s one of the longest workmanship guarantees in residential construction. Call (833) 630-4214 to start with the estimate.
Get a free estimate for your garage conversion
We’ll come out to your Miami property, measure the garage, check the slab and wall ties, and give you a written line-item estimate with the permit scope spelled out. No pressure, no vague number. Calls are answered by a live person around the clock, and the price we quote is the price you pay. Call (833) 630-4214 to schedule your free on-site estimate.