Garage Conversion ADU in Gladeview, FL: What It Costs and What’s Involved
A garage conversion ADU in Gladeview runs $45,000 – $130,000 and takes roughly 4 to 7 months from permit to final inspection. The low end is a straightforward living space with a bath and kitchenette; the high end adds a full kitchen, upgraded finishes, a separate utility meter and impact-rated doors and windows. Most of the older block garages we convert here sit at $70,000 – $95,000. Call (833) 630-4214 and we’ll walk your space and give you a written number.
How a Garage Conversion ADU Comes Together, Stage by Stage

Gut conversion on a 1950s concrete-block garage pays off in the sequence. Skip a step and you’ll pay for it twice.
Stage 1: Assessment and permitting (weeks 1 – 6). We measure the slab, check the wall thickness, and trace what’s buried in the floor and ceiling. You’ll decide here whether to keep the existing overhead door opening and frame it into a window wall, or close it entirely. Plans go to Miami-Dade County for review; that wait is not ours to rush.
Stage 2: Demolition and shell prep (week 6 – 8). Down come the old door, tracks, opener and any partition walls. We repair the block where fasteners and moisture have chewed it up. You’re not making a decision here, just watching us find out what the floor and walls actually look like.
Stage 3: Framing, slab and rough systems (weeks 8 – 13). Interior stud walls, the bathroom subfloor, then plumbing and electrical rough-in. Drying our climate makes slabs a controlled problem and that timer starts now. Your choices land here: kitchenette or full kitchen, where the shower sits, whether you want a stackable laundry closet.
Stage 4: Insulation, drywall and systems test (weeks 13 – 18). Closed-cell insulation, drywall hung and finished, then the rough inspections that have to pass before anything gets covered. This is the phase where a separate electrical service or the existing panel becomes a real conversation. You’ll pick the water heater type and any mini-split before walls close.
Stage 5: Finishes and final walkthrough (weeks 18 – 26). Flooring, tile, cabinets, paint, trim, and the final inspection. You sign off against the same line-item quote you started with, backed by our 730-Day Done Right Promise. Door hardware, outlets and light placement get settled in the last two weeks, not the first.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Options You’ll Actually Choose Between
- Kitchenette vs. full kitchen. A kitchenette (sink, mini-fridge, two-burner cooktop) keeps the budget near the low end. A full range, vent hood and dishwasher add cost and often demand a second 20-amp circuit and more plumbing. Renters love the full kitchen; family stays rarely need it.
- Impact-rated doors and windows. In Gladeview these aren’t optional upgrades for most of the opening. Impact-rated units and a matching window in the old overhead-door bay cost more than standard, but they’re the only versions that pass hurricane-zone inspection.
- Bathroom configuration. A walk-in shower keeps the footprint tight and slashes square footage. A tub needs more room and more materials. For a rental unit, the shower is usually the smarter spend.
- Water heater and HVAC. A tankless electric unit frees up closet space but needs adequate service capacity. A mini-split heats and cools one zone efficiently. You’ll choose both before walls close.
- Flooring. Porcelain tile suits South Florida humidity; luxury vinyl is warmer underfoot and easier to replace. Carpet in a converted garage is a mistake here and we’ll say so.
- Exterior finish. Stucco patched to match the CBS walls, fresh hardie-style cladding or a painted block finish. Paver aprons on the approach are a common add-on, and if you’re redoing the approach anyway, many homeowners pair this with Concrete Driveways & Concrete Work in Gladeview.
What Garage Conversion ADU Costs in Gladeview, FL

Residential garage conversions in Gladeview land between $45,000 and $130,000, with the typical project at $70,000 – $95,000. Where you land depends on five things:
- Garage size and slab condition. A single-car stall runs cheaper per square foot than a double. Original slabs with cracks or poor slope may need topping or replacement, which adds several thousand.
- Plumbing and electrical runs. If the garage shares a wall with the house’s wet wall, plumbing is short. If not, trenching and re-running lines pushes the job toward the high end.
- Structural work. Closing the door opening, adding a beam, reinforcing roof-to-wall connections on an older CBS garage. Any of these moves the number.
- Finish grade. Builder-grade vs. custom tile, cabinetry and fixtures is a wide spread. A curated set of brands like KraftMaid and Kohler sits in the middle of that range with predictable pricing.
- Permit scope. A habitable unit that needs its own electrical service or a new bathroom triggers more inspection stages. A studio with a kitchenette touches fewer.
Every written estimate we hand you is line-item and fixed. What’s included: demolition, framing, rough systems, insulation, drywall, finishes per your selections, permits and inspections. What isn’t always included: a separate utility meter, landscape repair, and appliances beyond the specified package. Call (833) 630-4214 for an exact quote. Estimates are free.
See the difference
Before
After
Before
After
Before
AfterWhat Gladeview Homes Specifically Do to This Job
Nearly every garage we convert in Gladeview, FL is a mid-century concrete-block structure under a run of Miami-Dade County permitting, and plenty of those block walls have aluminum-frame or jalousie openings that need impact-rated frames before the unit is legal. That’s the whole game here. The Florida Building Code’s High-Velocity Hurricane Zone requirements mean the new doors and windows are engineered for 150+ mph winds, not the lighter standards used elsewhere. On top of that, many of these pre-Andrew garages lack the roof-to-wall hurricane straps that HVHZ permitting now demands, so a “simple” conversion can pull a strapping retrofit into the job to pass inspection. We see it constantly on the CBS homes off NW 22nd Avenue and the side streets off NW 27th Avenue in ZIP 33147. The older the slab, the more we find moisture intrusion where the garage apron meets the wall, and the flat or low-slope roof that covers the garage is often the first thing failing. Subtropical rain and summer sun wear those surfaces fast, so a watertight roof is a prerequisite, not a later fix. If the conversion grows past the four walls into something larger, that’s usually where it becomes part of a full Home Additions & ADU in Gladeview scope. We cover the whole community through our Gladeview service page and handle this as one of our seven core lines under Home Additions & ADU.
Serving Gladeview, FL – Our Local Coverage Area
We serve Gladeview and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked Questions About Garage Conversion ADU in Gladeview

Expect 4 to 7 months from signed contract to final inspection, with the Miami-Dade County permit review eating 4 to 6 weeks of that. Construction itself is 12 to 18 weeks depending on how much rough plumbing and electrical the unit needs. Call (833) 630-4214 and we’ll give you a timeline specific to your garage.
Yes. Any garage becoming a habitable ADU in Gladeview requires a Miami-Dade County building permit and passing inspections, and the work falls under the Florida Building Code’s HVHZ requirements. We pull the permits and schedule every inspection. Skipping permitting puts the unit’s legal status and your insurance in a bad spot.
Sometimes. If your garage shares a wall with the house’s kitchen or bath, a bathroom and kitchenette can tie into existing lines with minimal trenching. If it doesn’t, expect plumbing runs, a subfloor and a few more inspection stages. The structural question – closing the overhead door and any beam or strapping work – is decided after we measure.
Garage conversions in Gladeview run $45,000 – $130,000, with most jobs landing between $70,000 and $95,000. Size, plumbing route, structural scope, finish grade and permit scope each push that number up or down. Call (833) 630-4214 for an exact quote; estimates are free.
Every conversion we build is covered by our 730-Day Done Right Promise – if it’s not done right, we make it right. That’s one of the longest workmanship guarantees in the residential construction space. All technicians are background-checked and uniformed. Ask for the written terms with your estimate.
Get a Free Estimate for Your Gladeview Garage Conversion
If you’ve got a garage doing nothing but collecting heat, it’s worth a real number. Call (833) 630-4214 for a free, no-pressure on-site estimate for a Garage Conversion ADU in Gladeview, FL. You’ll get a written line-item quote, a realistic schedule, and straight answers on permits and storm-hardening. Calls are answered by a live person 24/7. And if you’re redoing the drive approach as part of the project, we handle that too – homeowners often pair this with Asphalt Driveways & Resurfacing in Gladeview.