Concrete Driveways & Concrete Work in Gladeview, FL: What It Costs and How Long It Takes
A new concrete driveway in Gladeview runs $4,500 to $12,000 for most single-family lots in the 33147 ZIP code, and a full pour takes 3 to 5 working days from demolition to the day you can park on it. Concrete work here means slab replacement, aprons, approach strips, walkway extensions and new drive slabs poured to Miami-Dade County standards. Call (833) 630-4214 and we’ll walk your lot and put real numbers in writing.
How the job runs, from first cut to final cure

Concrete isn’t a one-day trade. Here’s the actual sequence we follow on a Gladeview driveway, with the decision points that belong to you.
Stage 1: Layout and saw-cut (half a day)
We string-line the new drive, mark the expansion joints and confirm the slope away from the garage and street. You approve the width and the apron radius before anyone cuts. If the old slab is tied into a CBS wall or a carport footing, this is when we decide how much stays.
Stage 2: Demolition and haul-off (1 day)
We break out the old concrete with a skid-steer breaker, load it and haul it off. On Gladeview’s older lots there’s almost always a root system underneath, and the crew roots-prunes anything that would push up through new concrete within a few years. You don’t decide anything here; it’s dirty work.
Stage 3: Base prep and compaction (1 day)
We excavate to 8 to 10 inches, bring in limerock base, and compact it in lifts with a plate compactor. This is the stage most cheap driveways skip, and it’s the exact reason hairline cracks show up two summers later. Miami-Dade’s sandy soil drains fast but shifts, so a properly compacted base and a moisture barrier matter more here than in clay country.
Stage 4: Form, steel and pour (1 to 2 days)
Forms get set, #3 rebar goes on a 16-to-24-inch grid (or welded wire mesh on lighter residential pours) and chairs hold it at mid-slab depth. You confirm the finish at this stage: broom, light salt, or saw-cut pattern. Then the pour itself, usually early morning to avoid the subtropical June-to-September heat that flash-sets concrete before finishers can work it.
Stage 5: Cure and seal (5 to 7 days)
Concrete cures, not dries. We keep it damp or covered for the first 48 hours, then you can walk on it in 24 to 48 hours and drive on it after 7 days. Full cure is 28 days. We come back for a final inspection and, if you chose it, apply a penetrating sealer once the slab has fully cured.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The concrete options you’ll actually decide between
Not every Gladeview lot should get the same slab. These are the real choices.
- Standard broom-finish slab, 4-inch thickness: $4,500 to $7,500 for a typical 2-car drive. Broom texture gives grip in the wet season and it’s the cheapest finish. Best for a rental duplex or a budget-minded single-family home.
- 6-inch slab with #3 rebar grid: pushes toward the $9,000 to $12,000 end. Worth it if you park a truck, a boat trailer or an RV. Thin mesh slabs fail fast under heavy loads.
- Saw-cut pattern or exposed aggregate: a mid-priced upgrade over broom. The cuts mimic large pavers and give the front of the house some visual weight without paying paver prices. If you want the real paver look, that’s a different trade and lives on our Driveway & Pavers in Gladeview page.
- Integral color: charcoal, sand, or terra cotta mixed into the pour, not painted on. Fades less than acid stain and holds up better in Florida sun. Tremron products are worth naming when we’re looking at colored hardscape on the rest of the yard, and Techo-Bloc comes into play if the plan includes a paver border along a concrete drive.
- Penetrating sealer: $250 to $700 as a standalone job, applied at 28 days. Cuts surface absorption, reduces rain staining, and slows the sun-induced surface chalk.
What Concrete Driveways & Concrete Work costs in Gladeview, FL

The working range is $4,500 to $12,000 for a new Gladeview driveway, with the midpoint sitting near $7,000 for a standard 20-by-30-foot pour at 4 inches with a broom finish. Driveway replacement when the demo is easy lands in the $5,000 to $14,000 bracket. Here’s what pushes a job up or down.
| Line item | Typical range |
|---|---|
| New concrete driveway, 4-inch, broom finish | $4,500 – $7,500 |
| 6-inch, rebar-reinforced, up to 3 cars | $8,000 – $12,000 |
| Full demo and haul-off, old slab | $800 – $1,800 |
| Saw-cut pattern or exposed aggregate finish | $1,200 – $3,000 additional |
| Integral color (per pour) | $600 – $1,500 |
| Penetrating sealer | $250 – $700 |
| Approach apron replacement (county-required section) | $1,500 – $3,500 |
The four variables that move the number: size (a 3-car drive is 50% more than 2-car), existing subbase condition (soft spots mean hauling in limerock and adding a day), access (a narrow lot off Northwest 22nd Avenue with no room for a concrete truck means a pump rental, $800 to $1,500), and whether other utilities or a carport are in the pour path. A written estimate includes the slab, base, rebar, forms, cutting, haul-off and cleanup. It usually does not include permit fees (Miami-Dade charges for right-of-way and approach work separately) or any plumbing or electrical relocation you add later.
Homeowners often pair this with Door Installation in Gladeview while the front of the house is torn up, since the same access and timing works in the crew’s favor.
See the difference
Before
After
Before
After
Before
AfterWhat Gladeview homes specifically do to this job
Gladeview is unincorporated, so nearly every permit runs through Miami-Dade County rather than a city building department, and the Florida Building Code’s High-Velocity Hurricane Zone requirements apply here just as they do on the coast. That shifts concrete work in ways a buyer moving from another state won’t expect: approach aprons on the county right-of-way need engineering review, and any slab tied into a CBS structure may trigger a wind-load detail. Then there’s the housing stock. Most of these lots hold mid-20th-century concrete-block homes and duplexes built before Andrew, and the original driveways poured with them are 40 to 60 years old, often 3-inch slabs with no steel and no joint sealer, cracking along the path the truck took in 1965. We see the same failures block after block off Northwest 27th Avenue and along the edges of Brownsville: corner cracks from root lift, spalling where the surface was never sealed, and hollow-sounding slabs from years of heavy rain pushing through a thin base. Our Driveway & Pavers service covers the broader hardscape if you’re planning to extend past the drive; for the pour itself, the fix is usually a full replace rather than patching a 50-year-old slab that was never built to today’s standard.
Homeowners often pair this with ADU Site Prep & Utilities in Gladeview when the new drive coincides with a rear structure or utility trench that needs concrete restoration.
Serving Gladeview, FL – Our Local Coverage Area
We serve Gladeview and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked – Concrete Driveways & Concrete Work in Gladeview

Three to five working days from demolition to walkable surface, plus 5 to 7 days before you can drive on it. Weather pushes it. A summer afternoon storm that drops two inches in ninety minutes can cost a day waiting for curing time, so we schedule around the June-to-September pattern where we can.
Yes for a new driveway apron that ties into the county right-of-way, and yes for any structural work tied into the home. A same-size slab replacement inside the property line sometimes skips the permit, and we’ll tell you honestly which side of that line your job falls on when we do the estimate. We pull what’s required, and we don’t start until the permit is in hand.
Only if the existing slab is structurally sound, level, and correctly drained, which is rare on a Gladeview slab past its fortieth year. A pour-over adds 4 to 6 inches of height, breaks the garage transition, and traps any moisture problem underneath. The honest answer is almost always full replacement.
Not on a fixed-price contract. The number we write down is the number you pay unless you add scope. If we open the base and find soft soil or an undocumented utility line, that’s a conversation before any extra work, in writing, not a surprise invoice.
$4,500 to $12,000 for most single-family Gladeview lots, and every job comes with our 730-Day Done Right Promise: if it’s not done right, we make it right. Call (833) 630-4214 for an exact quote. Estimates are free and on-site.
Get a free estimate for your Gladeview pour
Call (833) 630-4214 and a live person picks up, any hour, any day. We’ll set a site visit for Gladeview, measure the drive, check the base, confirm what permits apply, and hand you a written line-item estimate with fixed pricing. No pressure to sign on the spot. Free estimates, and the price we quote is the price you pay.